An archival view of the unfinished Sagrada Família with scaffolded towers above its Nativity side. Buy Art Prints Now
from Amazon

* As an Amazon Associate I earn from qualifying purchases.


The unfinished Nativity façade in a photograph catalogued in 1926. Unidentified photographer, Spaarnestad Photo. Image source. Public domain. Resized for the web.

by
Tom Gurney BSc (Hons) is an art history expert with over 20 years experience

Email: tomgurney1@gmail.com / Phone: +44 7429 011000

How the Sagrada Família Was Built: Introduction

Barcelona’s Sagrada Família began on 19 March 1882 with a cornerstone for a neo-Gothic church designed by Francisco de Paula del Villar. By the time Antoni Gaudí took charge the following year, the foundations of the crypt were laid and its columns were partly built. Gaudí spent the next four decades redesigning and building the church. His successors inherited a partly built façade, a workshop full of models and the task of raising a building far larger than the one Villar had planned. [1] [2] [3]

At a Glance

  • LocationBarcelona, Spain
  • Construction began19 March 1882
  • Founding initiativeJosep Maria Bocabella and the Spiritual Association of the Devotees of Saint Joseph
  • First architectFrancisco de Paula del Villar
  • Gaudí’s tenure1883–1926
  • First completed bell towerSaint Barnabas, on the Nativity façade, 1925
  • Basilica dedicated7 November 2010
  • Jesus Christ towerExterior completed on 20 February 2026 and blessed on 10 June 2026

This work across Antoni Gaudí’s career

Project dates
18751888190119141926

How the Sagrada Família Was Built (current article)

Sagrada Família, Gaudí’s tenure 1883–1926 and later work

Casa Vicens

1883–1885: Original summer house

Sagrada Família

1883–1926: Gaudí’s tenure

Palau Güell

1886–1890: Main building campaign

Park Güell

1900–1914: Residential estate works

Casa Batlló

1904–1906: Remodelling

Casa Milà

1906–1912: Apartment house

Church of Colònia Güell

1908–1915: From the start of building work to the opening of the lower church

Contents

  1. Villar’s church and Gaudí’s first changes
  2. Building upwards at the Nativity façade
  3. What the workshop left behind
  4. The 1936 losses and the return to work
  5. From the Passion towers to the roof over the nave
  6. Lighter stone for the central towers
  7. The cross, the blessing and the work that followed

Villar’s church and Gaudí’s first changes

The building began with a fundraising campaign. Josep Maria Bocabella, a Barcelona bookseller, founded the Spiritual Association of the Devotees of Saint Joseph in 1866. Its magazine publicised the cause and solicited donations, and the priest Josep Manyanet helped promote the idea of a church dedicated to the Holy Family. In 1881 the association acquired a site in El Poblet, then in Sant Martí de Provençals. It commissioned the diocesan architect Villar to design an expiatory church, with construction financed by the offerings of the faithful. Bishop Urquinaona laid the cornerstone on Saint Joseph’s Day the following March. [1] [2] [3]

Villar proposed pointed windows, flying buttresses and a tall, pointed bell tower. The work began below ground, with a semicircular crypt beneath the apse. Disagreements over the work, including the cost of materials, led to his departure. When Gaudí took charge on 3 November 1883, he kept the crypt’s footprint and much of its neo-Gothic design. He changed how people would circulate between levels, replacing the proposed stairs with two spiral staircases and putting sacristies at their feet. He raised the vault and excavated around the outer wall to admit daylight and reduce damp. Mass was celebrated in the Saint Joseph chapel in 1885, four years before the crypt was completed. [1] [3] [4]

Above the crypt, the apse façade shows how gradually the project changed. Its pointed windows and prominent buttresses belong to the Gothic vocabulary Gaudí inherited. Gargoyles in the shapes of Mediterranean animals channel rainwater away from the roof. The basilica’s booklet dates the main work on the apse façade to 1890–93, while the Consell Antoni Gaudí records completion in 1894. The Consell also credits a substantial anonymous gift with giving Gaudí room to expand the scheme. The resulting design retained the familiar Latin-cross plan while making room for a much larger church and a hierarchy of towers. [2] [4] [5]

Building upwards at the Nativity façade

Work on the Nativity façade began in the early 1890s, while the apse was still taking shape. Gaudí concentrated labour on one section that could rise far above the rest of the site. That gave future builders a full-size example of the stonework, sculpture and pinnacles, and gave supporters a visible measure of what their donations had made possible. The institution that managed those gifts also changed. After Bocabella and his son-in-law Manuel de Dalmases died, the Junta Constructora was established in 1895 to oversee the finances and keep construction going. [1] [2] [3] [5]

The Rosary portal, an entrance to the cloister beside the Nativity façade, was completed in 1899. A model of the façade was shown at the Grand Palais in Paris in 1910, in an exhibition backed by Eusebi Güell. Original photographs of the exhibition survive in the Càtedra Gaudí at the Universitat Politècnica de Catalunya. They record how a work still rising in Barcelona could be presented as a whole to an audience abroad. [5] [6]

From 1914 the temple became Gaudí’s sole architectural project. He was still developing its overall design. In 1916 he submitted proposals to the city for the space around the church, and in 1923 he settled on a design for the naves and roofs. Near the end of his life he lived by the site workshop, where architects, draughtsmen, sculptors and model makers worked on designs that could be tested in plaster while work on the Nativity front continued. By 1925 the bell tower dedicated to Saint Barnabas stood complete. It was the only one he saw finished. When he died on 10 June 1926, the Nativity front already gave a substantial impression of the scale and finish he sought. Much of the design for the body of the church still existed in the workshop. [1] [2] [5]

Two men stand near a wall in front of the Sagrada Família construction site, with bare masonry beyond.
Baldomer Gili i Roig photographed the Sagrada Família in 1905 while the early stonework was rising above the surrounding plot. Baldomer Gili i Roig, Museu d’Art Jaume Morera. Image source. Public domain. Resized for the web.

An archival view of the unfinished Sagrada Família with scaffolded towers above its Nativity side.
A Spaarnestad archive photograph catalogued in 1926 shows scaffolding around the rising Nativity façade and the lower parts of the temple exposed. Unidentified photographer, Spaarnestad Photo. Image source. Public domain. Resized for the web.

What the workshop left behind

The workshop held studies at different scales and from different moments in the design. A small study could show how a capital met the stonework above or how a window opened through a vault. A larger assembly showed how those pieces belonged together. The 2023 exhibition checklist of the National Museum of Modern Art, Tokyo, identifies a 1:10 model of a central-nave capital and architrave, dated about 1913–15 and catalogued as a second version. Gaudí was revising the interior while work went on elsewhere. Even a surviving model has to be dated and placed within that sequence before it can be used to explain the building. [7]

The structure of the nave also survives in a different kind of record. Gaudí’s colleague Domènec Sugranyes published a description of its design and stability calculations in 1923. The structural historian Santiago Huerta reads it alongside the surviving images of the plaster models. In the calculations, portions of the building were treated in groups whose weights could be estimated and assigned to particular branches of the columns. Those branches gathered loads from several points overhead and carried them down to fixed positions. The footprint Gaudí inherited helped determine where that system could meet the ground. [8]

The drawings explain some of the branching geometry visible inside the church. They also show why the famous hanging model associated with Gaudí can mislead here. Huerta distinguishes the suspended model developed for the church at Colònia Güell from the graphical equilibrium studies and plaster models used for the Sagrada Família nave. He also questions one simplification in Sugranyes’s account, which treated the vault loads as though they produced no sideways thrust. The published study preserves a way of thinking about the structure, with assumptions that later engineers could examine. [8]

Sagrada Família workshop under a brick vault with plaster models, shelves and worktables.
Models and pieces in the Sagrada Família workshop in a photograph dated 1926. Treated as a period record, it helps show the range of material kept indoors. Unidentified photographer, via Maria Antonietta Crippa, Gaudí. Image source. Public domain. Resized for the web.

The 1936 losses and the return to work

Sugranyes took charge after Gaudí’s death. Under him the other three Nativity bell towers were completed and work advanced on the Faith portal and central cypress. In a photograph from 1933 reproduced in the Junta’s construction booklet, the towers dominate a site where the main body of the church has yet to rise. [1] [2] [5] [9]

In July 1936, at the outbreak of the Spanish Civil War, the crypt and the provisional schools were set on fire and the workshop was wrecked. Drawings, plans and photographs burned, and plaster studies were smashed. The fire left the crypt in need of repair. In the workshop, surviving pieces of plaster had to be found, sorted and fitted together. Published photographs and plans preserved elsewhere helped fill gaps in the design record. The Junta’s archive still holds four volumes of the Àlbums del Temple, published between 1914 and 1929, which became working references for the building campaign. [1] [3] [5]

The official chronology dates Francesc de Paula Quintana’s assumption of site management to 1939. The archive dates the resumption of work and the search for fragments and original plans to 1940. Quintana repaired the crypt and led former collaborators and disciples in assembling the evidence again. A piece of plaster could yield a curvature that a photograph flattened. A photograph might preserve the relation of that piece to neighbours that had disappeared. A plan could supply a dimension neither of the other sources readily gave. The postwar plans collection contains drawings made by the architects and surveyors who had to turn that uneven evidence into instructions for the site. [1] [3] [5]

The Tokyo checklist gives a sense of the span of this workshop tradition. Alongside Gaudí’s earlier study of the central-nave capital, it lists a 1:10 model of the side-aisle columns and vaults made by the basilica’s model shop in 2003. Both objects represent the church at one-tenth of full size. Their dates and makers distinguish an early study for the central nave from a later workshop’s study for the side aisles. [7]

Watch films on Gaudí’s architecture

Explore the Sagrada Família, Casa Milà and Casa Batlló, then consider Gaudí’s place in European Art Nouveau.

A postcard shows the four Nativity towers and lower parts of the unfinished basilica.
This postcard reproduced by Leo Wehrli shows how the completed Nativity towers dominated the still unfinished church. Leo Wehrli, ETH-Bibliothek Zürich, Bildarchiv, Dia_247-16021. Image source. CC BY-SA 4.0. Resized for the web. This reproduction uses the same CC BY-SA 4.0 licence.

From the Passion towers to the roof over the nave

Under Quintana, the focus of new construction moved across the site. He worked closely with architects Isidre Puig i Boada and Lluís Bonet i Garí on the Passion façade, drawing on studies Gaudí had left. Foundations were laid in 1954, and a fundraising collection followed in 1955. Work at Nativity continued, and in 1958 Jaume Busquets’s Holy Family group was put into place. Puig i Boada and Bonet i Garí took charge after Quintana died in 1966. By 1976 all four Passion bell towers were finished. The commission for Josep Maria Subirachs’s sculpture came in 1986. The dates explain why a photograph can show the four towers standing above a façade still awaiting much of its sculpture. The guide to the Sagrada Família façades follows that work and the artists who carried it out. [1] [2] [9]

Construction on the side-nave façades began in 1978. Francesc Cardoner i Blanch took over in 1983 and Jordi Bonet i Armengol was appointed head architect in 1985. Bonet assembled a team for the nave campaign that included Carles Buxadé, Joan Margarit, Josep Gómez, Jordi Coll, Mark Burry and Jordi Faulí. The builders laid foundations, raised columns and walled and vaulted the principal spaces, including the crossing and apse. The vaults over those last two areas were completed between 2008 and 2010. On 7 November 2010 Pope Benedict XVI dedicated the church for worship and declared it a minor basilica. The building had a usable interior while the central towers and principal entrance remained ahead of the builders. [1] [2] [5] [9]

Computer modelling changed what the workshop could do with partial evidence. In a 1996 paper, architect Mark Burry described work on the triforium, a gallery above the aisles. Starting with surviving plaster fragments and the geometries Gaudí was known to use, Burry varied the dimensions of related surfaces in a digital model to find forms consistent with that evidence. A change in curvature could be tested against neighbouring surfaces and against the form of the surviving plaster. [10]

The Passion entrance porch posed a different problem. Gaudí had produced a pencil-and-gouache design known from a photograph and died before he could model the porch in plaster. Mark and Jane Burry used the photograph to interpret the design in three dimensions, applying geometries from his late work. Their project went from a small sectional model to files suitable for computer-controlled stonecutting. Work on the main colonnade and the horizontal stonework it supports began in 2009. Here the computer helped carry an interpretation from a historical image to fabrication. The Sagrada Família overview explains how the porch, nave and crossing fit into the building as a whole. [11]

In 2005 the World Heritage Committee added the Nativity façade and crypt to the serial listing for the Works of Antoni Gaudí. Those are the Sagrada Família components named in the decision. The inscription concerns early fabric that successive builders have also had to maintain, even as their colleagues elsewhere on the same site add new stone. [12]

Lighter stone for the central towers

Jordi Faulí succeeded Jordi Bonet as head architect in 2012. The Junta dates the start of its campaign on the six central towers to 2016, the year it records the completion of the western sacristy and the adjoining cloister of Our Lady of Dolours. The Foundation brought in Arup in 2014 to work on the remaining structural design. The Virgin Mary tower presented two linked problems. Its form had to be interpreted from fragmentary evidence, using the geometry of Gaudí’s sacristy model as a guide. Its weight had to stay within what the existing foundations could carry. When the engineers tested ordinary masonry thin enough to meet that limit, severe winds put parts of the stonework into tension, where it is vulnerable to opening at the joints. [1] [2] [13] [14]

The engineers responded by assembling blocks into panels and threading stainless-steel rods through the stone. Tensioning the rods squeezed the blocks together before the panels left the workshop. Under wind loads the stone could then stay largely in compression, where it is strongest. In the Virgin Mary tower study, the scheme allowed the team to use stone about 30 centimetres thick, against roughly 1.2 metres in the conventional masonry comparison. Full-scale mock-ups helped check the appearance and the practical fit. Cranes lifted fabricated panels into position to form rings, with engineered joints between them. Moving assembly into a factory also freed up space on a crowded site that still had to admit visitors. Mid-twentieth-century photographs in the Junta booklet show how different the site once looked, with timber scaffolding enclosing stonework built in place. [2] [13] [14]

Devotional gifts had financed the first building campaigns. By 2025 the Junta still reported entirely private funding, but visitors accounted for 96.9 per cent of its €134.5 million income. The dependence on visits had become apparent in March 2020, when the COVID-19 emergency stopped construction and closed the church to visitors. The Junta later reported that the closure had cut its income sharply. Work resumed in October, concentrating on the Virgin Mary tower. Its star was first lit on 8 December 2021. Mark and Luke’s towers were completed in 2022, John and Matthew’s in 2023. The four Evangelist towers were blessed and illuminated together on 12 November 2023. [1] [2] [15] [16]

The cross, the blessing and the work that followed

Faulí dated the setting of the first panels of the Jesus Christ tower to 16 October 2018, when they went in 85 metres above ground. The cross required another structural solution. Stainless-steel ribs and a thin shell of high-performance concrete work together behind the ceramic surface, leaving room for the interior Gaudí envisaged. The engineers tested full-size sample panels to see how the materials behaved together. Modules made in Germany arrived for pre-assembly on a platform above the nave, 54 metres off the ground. Workshops in Catalonia supplied its white glazed ceramic, interior stonework and glass. The cross went up in seven pieces, with the core and each arm lifted separately. The builders set the upper arm in place on 20 February 2026, completing the tower’s exterior and bringing the basilica to 172.5 metres. [14] [17] [18] [19]

Pope Leo XIV blessed the tower on 10 June 2026, a hundred years after Gaudí’s death. The inauguration included the first lighting of the cross. [19]

On 24 July the Junta reported that the central crane was being lowered to 174 metres and would chiefly serve the Glory bell towers. Its jib had reached 203 metres during the work on the Jesus tower. With the crane lower, the builders could dispense with its brace to the completed tower exterior. [20]

On 22 September the Junta reported work on the tower interior, designed to represent the heavens, and said that a lift still had to be installed. Elsewhere, work was proceeding at the Glory façade, conceived by Gaudí as the main entrance, and at the Chapel of the Assumption, or Assumpta, with adjoining stretches of cloister on Carrer de Provença. [19] [21]

At the chapel, the stone vault for a gallery eight metres above ground was already in place. The team had made exterior figures including Saint Joseph Oriol, Saint Roch and angels associated with the dome and the Virgin’s mantle. The report also recorded continuing conservation on the Nativity façade and announced restoration work to come on the Simon bell tower. The two jobs were proceeding side by side, with stone going up at the future entrance while the earliest façade required conservation. [21]

The Junta’s November 2026 construction booklet charts the six central towers as the milestone reached that year and the remaining major phase, including Glory, as still under construction, with its completion date to be determined. As of 21 November 2026, the September report remains the latest detailed site update on the chapel, tower interior and planned lift. [2] [21]

Browse the buildings and designs

Explore Gaudí’s buildings, landscapes and designed objects, alongside lost works and projects known through documents. The entries identify collaborative and attributed work where relevant.

32 records

NameDatePlace, use and survival
Casa Vicens1883–85, original houseSummer house with a later enlargement.
Güell Pavilions and Estate1880sEstate entrance and service buildings. The site and gardens changed in later campaigns.
Palau Güell1886–90, main campaignRestored urban mansion in the Raval.
Teresian CollegeLate 1880sCollege and convent adapted from an earlier project. The existing annex chapel is by Gabriel Borrell i Cardona.
Casa CalvetLate 1890sTextile premises and dwellings.
Torre BellesguardEarly 1900sHouse and site works beside traces of an earlier royal residence.
Park Güellc. 1900–14, estate worksPartly realised residential estate, later a public park.
Gaudí House MuseumEarly 1900s; Gaudí lived here 1906–25Estate show house designed by Francesc Berenguer, later Gaudí’s residence.
Portal MirallesEarly 1900sSurviving estate gateway and a length of enclosing wall.
Casa Batlló1904–06, remodellingRemodel of an existing residential building.
Casa Milà1906–12Apartment block, later restored.
Sagrada FamíliaBegun 1882; Gaudí from 1883Basilica built in successive campaigns under Gaudí and other architects.
Sagrada Família SchoolsEarly 1900s, original schoolSchool subsequently rebuilt and relocated on the site.
Plaça Reial Lampposts1878 commission; installed 1879Municipal street furniture.
Sant Pacià Mosaic PavementLate 1870sTessellated church pavement.
Nau Gaudí and the Mataró Workers’ Cooperative1883, bleach hallMataró. Restored bleach hall and a separate surviving latrine building within a larger scheme.
Bodegas Güell1890sGarraf. Winery and service buildings, with drawings credited by the architects’ archive to Gaudí and Francesc Berenguer.
Church of Colònia GüellBegun 1908; lower church opened 1915Santa Coloma de Cervelló. Lower church of a partly realised design.
Jardins ArtigasEarly 1900sLa Pobla de Lillet. Restored riverside garden.
Xalet del CatllaràsEarly 1900sLa Pobla de Lillet. Lodge associated with the mines. Research published by the Consell distinguishes Gaudí’s design from decisions made in execution.
First Mystery of Glory at MontserratEarly 1900s, first campaignMontserrat. Monument to the Resurrection in a larger devotional ensemble, executed in phases.
El Capricho de Gaudí1880sComillas. Summer villa, subsequently restored.
Puerta de los PájarosEarly 1900s, attributedComillas. Casa del Moro boundary gate, locally attributed to Gaudí.
Casa Botines1891 drawings; building work in 1892León. Commercial and residential building, later converted to new uses.
Episcopal Palace of Astorga1889–93 under Gaudí; finished 1913Astorga. Palace begun under Gaudí and finished by Ricardo García-Guereta.
Gaudí’s Restoration of Mallorca CathedralEarly 1900sPalma. Liturgical intervention in an existing cathedral.
Bar Torino1902, Passeig de Gràcia interiorBarcelona, Passeig de Gràcia. Lost collaborative bar interior.
Compañía Trasatlántica Pavilion1888, Barcelona expositionBarcelona, 1888 Universal Exposition. Lost exhibition building.
Banner of Misericòrdia1900Reus. Lost pilgrimage banner designed by Gaudí with a painting by Aleix Clapés.
Franciscan Missions in TangierEarly 1890sTangier. Documented unbuilt mission complex.
Hotel Attraction and Its AttributionPosthumous drawings of the 1950sNew York. Unbuilt hotel associated with Gaudí through posthumous drawings. The commission is uncertain.
Capilla de Nuestra Señora de los Ángeles1922 correspondence; later proposalRancagua. The historic proposal was unbuilt. A later Chilean project drew on Gaudí’s Barcelona chapel design.

Frequently Asked Questions

Who started building the Sagrada Família?

The association founded by bookseller Josep Maria Bocabella commissioned Francisco de Paula del Villar. Building began with the crypt in 1882. Antoni Gaudí took over in November 1883 and developed the much larger scheme associated with the basilica today. [2] [3] [4]

What survived the destruction of Gaudí’s workshop?

Fragments of plaster models were recovered, and published photographs and plans supplied evidence for rebuilding. Early material survived outside the workshop as well. The Gaudí Chair’s archive, for instance, holds original photographs of the 1910 Paris exhibition. Together these records made it possible to resume work, with later architects responsible for reconstructing and interpreting missing parts. [1] [3] [6]

Did the Sagrada Família finish construction in 2026?

The Jesus Christ tower reached its full exterior height on 20 February and was blessed on 10 June. The September construction update still recorded interior work, a lift to be installed, and ongoing construction at Glory and the Assumpta chapel. The construction booklet available in November leaves the basilica’s completion date open. [2] [18] [19] [21]

Discussion

Look again at the images and ideas explored in How the Sagrada Família Was Built. These editorial prompts invite your observations.

Reader Insights

Editorial prompt · Read the site from the ground up

How did the partly built crypt shape what Gaudí could change, and why did he put so much of the early work into one façade?

Editorial prompt · Compare a fragment and a photograph

If you were reconstructing a broken model of a vaulted bay, which features would you measure from the plaster and which could you recover from an old photograph?

Editorial prompt · Date a building in use

Which parts of the building’s history would you mark with 1885, 2010 and 2026? What became usable or visible at each point?

Join the Conversation

Share a detail, comparison or question about How the Sagrada Família Was Built below.

References

  1. Junta Constructora, History of the Temple View source.
  2. Daniel Giralt-Miracle and the Junta Constructora, Brief History of Temple Construction, information booklet 2, November 2026 edition View source.
  3. Junta Constructora, Heritage Assets, administrative archive and plans library View source.
  4. Junta Constructora, Crypt, Apse Façade and Chapel of the Assumption, information booklet 5 View source.
  5. Consell Antoni Gaudí, Temple Expiatori de la Sagrada Família View source.
  6. Universitat Politècnica de Catalunya, Gaudí Chair and ETSAB collections View source.
  7. National Museum of Modern Art, Tokyo, Gaudí and the Sagrada Família exhibition checklist, nos. 88–89, 2023 View source.
  8. Santiago Huerta, Structural Design in the Work of Gaudí, Architectural Science Review 49, no. 4, 2006, pp. 324–339 View source.
  9. Daniel Giralt-Miracle and the Junta Constructora, Gaudí and His Followers: The Workshop, information booklet 3 View source.
  10. Mark Burry, Parametric Design and the Sagrada Familia, Architectural Research Quarterly 1, no. 4, 1996, pp. 70–81, abstract View source.
  11. Jane Burry and Mark Burry, Narthex Study and Passion Facade Model, La Sagrada Familia, RMIT University View source.
  12. UNESCO World Heritage Committee, Decision 29 COM 8B.47, 2005 View source.
  13. Tristram Carfrae speaking to Hugh Ferguson, Completing the Sagrada Família, Ingenia 81, December 2019 View source.
  14. Arup, La Sagrada Família: A Collaboration in Digital and Stone View source.
  15. Junta Constructora, Annual Report 2025, income and expenses View source.
  16. Junta Constructora, Sagrada Família and City Council Agree to Change Calendar for Temple’s Financial Commitments, 17 February 2021 View source.
  17. Junta Constructora, Blessing and Inauguration of the Tower of Jesus Christ, 21 May 2026 press conference View source.
  18. Junta Constructora, Cross Lands in Sky Above Barcelona, 20 February 2026 View source.
  19. Junta Constructora, Pope Leo XIV Blesses Tower of Jesus Christ, 10 June 2026 View source.
  20. Junta Constructora, New Stage for Sagrada Família Central Crane, 24 July 2026 View source.
  21. Junta Constructora, Sagrada Família Advances in Final Phase of Construction, 22 September 2026 View source.